Skip to the main content
Sammamish Town Center (not licensed)

2024 ADA Barrier Removal Project

Project Engineer

Joe Dapcevich
(206) 572 0595

Construction Inspector

Jim Krieg
(425) 495 7962


Summary

The City of Sammamish 2024 ADA Barrier Removal Project consists of upgrading non-ADA compliant facilities along 228th Avenue SE, within the City’s right-of-way, at the following locations: 

  • Sidewalk Repairs Between SE 8th Street and SE 32nd Street
  • Curb Ramp Removals at the SE 13th  Street Intersection
  • Curb Ramp Removals & ADA Retrofits at the SE 27th Street Intersection

The retrofits and repairs will include removing and replacing existing concrete curb, concrete sidewalk, curb ramps, asphalt pavement, traffic control devices, and/or roadway striping.   

This project is part of the City of Sammamish ADA Transition Plan. The purpose of the plan is to identify and remove barriers which impede access to City buildings, parks, and pedestrian facilities in the public right-of-way. For more information on the ADA Transition Plan, visit the link below.

https://www.sammamish.us/projects/ada-transition-plan/

 


Construction Information 

Timeline

Updated September 24, 2024

All work for this project has been completed.

Work Description

Dates

Site Preparation & Notifications

July 15 – July 17

Sidewalk Sites 14 - 19

West Site A Curb Ramps

July 17 – August 14

East Site B

Sidewalk Sites 22, 23, 27

August 23 – August 27

Sidewalk Sites 20-21

August 28 – September 3

East Site A

September 4

West Site B

September 4 – September 5

Site C

September 5 – September 11

Site Restoration

September 9 – September 11

Site B & C Roadway Striping

September 24

Hours of Work

Construction generally starts at 7:00 am and ends at 5:00 pm, Monday through Friday. If construction continues into the school year, work hours will be reduced to 9:00 am to 3:00 pm. Actual start and end times may vary slightly depending on construction progress. 

Traffic Control

All streets will remain open throughout construction. Traffic along 228th Avenue SE will often be reduced to a single lane. Portable message boards will be installed prior construction to inform drivers of lane closures.  

School Bus Routes

If construction continues into the school year, school bus routes and schedule will not be changed. We will be working with the contractor and  local school districts to ensure unimpeded service in all neighborhoods.