228th Avenue Curb Ramp Retrofit and Catch Basin Repairs

Post-Concrete Pour.JPG

OVERVIEW

Curb ramp retrofits and sidewalk repairs are a critical component of maintaining our current roadway network.  Per the ADA laws that went into effect in 2009, all street crossings with an overlay that crosses an intersection must improve all curb ramps to meet the current standards specified in the Americans with Disabilities Act.  This project is designed to update all crossings on 228th Avenue between SE 8th St and NE 8th St before we overlay in 2022.  This project also incorporates repairing every catch basin within the corridor in order to avoid emergency repairs after the new pavement layer is placed.  The City opened bids on March 4, 2021.  Eight contractors submitted bids and the lowest, responsible bidder is Axum General Construction, Inc.

construction Schedule

A construction schedule will be posted after the project has been awarded. 

Note: The work dates listed are subject to change due to weather, equipment and occasional other scheduling conflicts.

PROJECT TIMELINE

Design Completed: January 31, 2021
Advertised for bidding: February 11, 2021
Bid Opening: March 4, 2021
Anticipated Project Award: April 6, 2021
Est. Preconstruction Meeting: Week of April 12, 2021
Begin Construction/NTP: Week of April 19, 2021
Substantial Completion: TBD
Estimated Project Completion: Fall 2021

PROJECT CONTRACT TOTAL

Axum General Construction: $1,096,145.70

PROJECT PROGRESS

0.0% Completed

PROJECT PROGRESS

2021 Curb Ramp Retrofit - Bid Tab (preliminary)
2021 Curb Ramp Retrofit - Plan Set
2021 Curb Ramp Retrofit - Project Specifications
2021 Curb Ramp Retrofit - Addendum 1
2021 Curb Ramp Retrofit - Addendum 2

Updated: BR 03.25.21

Staff Contact