Segment 2B
East Lake Sammamish Trail Segment 2B Shoreline Substantial Development Permit (SSDP2016-00415)
STATUS UPDATE (01/31/2019): Following closure of the public hearing on November 20, 2017, the City of Sammamish Hearing Examiner (HE) issued a decision of denial dated January 5, 2018 on the Shoreline Substantial Development Permit (SSDP) for phase 2B of King County’s East Lake Sammamish Regional Trail (KC ELST 2B).
This City HE Decision was appealed to the Washington State Shorelines Hearing Board (SHB) on January 31, 2019 by multiple parties, including King County, and assigned SHB file No. 18-004c. Following completion of the State SHB appeal hearing process, the SHB ruled on November 7, 2018 in its written decision that the City shall approve the SSDP (City File No. SSDP2016-00415) for the KC ELST 2B in accordance to the Board’s direction.
Following the SHB ruling, and after transmittal to the City’s HE, the HE issued a new decision on January 31, 2019 approving the SSDP for the KC ELST 2B subject to conditions. There is no further appeal period opportunity relating to this SSDP. The Washington State SHB and the City HE decisions are included below.
The City HE and the Washington State SHB decisions on the SSDP are planning level decisions and do not authorize construction activity. The applicant and project proponent, King County Parks, must apply for and receive construction permit(s) before work may commence to build the new trail segment.
City staff have been in communication with King County and it is estimated that King County will provide construction permit application sometime in the end of February. King County’s application for construction permits will include the 90% construction plans/project design. At that time staff will begin review of the construction permit application and supporting materials for compliance with the January 31, 2019 City HE SSDP.
JANUARY 31, 2019 CITY OF SAMMAMISH FINAL HEARING EXAMINER DECISION ON SSDP
January 31,2019 SSDP2016-00415b_Hearing_Examiner_Decision
NOVEMBER 7,2018 SHORELINE HEARING BOARD FINDINGS OF FACT, CONCLUSION OF LAW AND ORDER.
November 7, 2018 East Lake Sammamish Trail Segment 2B - Shoreline Hearing Board Findings and Order:
JANUARY 23, 2018 OFFICIAL FILING LETTER RECEIVED FROM DEPARTMENT OF ECOLOGY
January 23, 2018 OFFICIAL FILING LETTER
JANUARY 23, 2018 NOTICE OF TRANSMITTAL TO DEPARTMENT OF ECOLOGY
January 23, 2018 Notice Issued to Parties of Record
JANUARY 23, 2018 TRANSMITTAL TO DEPARTMENT OF ECOLOGY
January 23, 2018 Transmittal to Department of Ecology
January 23, 2018 Transmittal Data Sheet
JANUARY 5, 2018 NOTICE OF HEARING EXAMINER DECISION
January 5, 2018 Notice Issued to Parties of Record
CITY OF SAMMAMISH HEARING EXAMINER DECISION
Description
The City of Sammamish received an application on October 19, 2016, requesting a Shoreline Substantial Development Permit (SSDP) to improve 3.5 miles of the existing soft-surface interim East Lake Sammamish Trail, extending from SE 33rd Street to Inglewood Hill Road. This interim trail will be widened to 12 feet of paved surface with 2-foot gravel shoulders and a 1-foot clear zone on both sides.
In conjunction with the trail widening, associated activity will take place which includes: earthwork; drainage improvements related to the trail; culvert replacements to improve fish passage; construction of rest areas with benches; improved intersections and sight triangles; mitigation and habitat enhancement; landscaping and fencing; and access and traffic control (bollards, striping, signage, etc.).
The subject properties are located in the R-4 zone and in close proximity to Lake Sammamish which is a Shoreline of Statewide Significance. This proposal is located within the Lake Sammamish Shoreline Residential Environment Designation. An SSDP is now a Type 4 process which includes a Staff Recommendation and Final Decision by the City’s Hearing Examiner.
- November 7, 2018 East Lake Sammamish Trail Segment 2B - Shoreline Hearing Board Findings and Order: 4.04 MB - November 7, 2018 SSDP2016-00415 Shoreline Hearings Board FIndings and Order
Hearing Examiner - Public Hearing Audio
- November 3rd, 2017 - East Lake Sammamish Trail - Segment 2B Public Hearing
- November 6th, 2017 - East Lake Sammamish Trail - Segment 2B Public Hearing
- November 7th, 2017 - East Lake Sammamish Trail - Segment 2B Public Hearing
- November 20th, 2017 - East Lake Sammamish Trail - Segment 2B Public Hearing (1)
East Lake Sammamish Trail Segment 2B - Exhibits Submitted After Closing of Public Hearing
- Exhibit 130 - King County/Bill Schultheiss Rebuttal Testimony Dated November 30, 2017: 620 KB
- Exhibit 131 - City's Closing Argument: 1.47 MB
- Exhibit 132 - King County's Closing Argument: 1.47 MB
East Lake Sammamish Trail Segment 2B - Exhibits Submitted During Hearing
- Exhibit 71 - King County Memorandum: 9.24 MB
- Exhibit 72 - King County Trails Map: 359 KB
- Exhibit 73 - King County Regional Trails Plan: 20.11 MB
- Exhibit 74 - King County Regional Trail Guidelines: 30.14 MB
- Exhibit 75 - W. Beres comment: 3.41 MB
- Exhibit 76 - A. Meerscheidt comment: 167 KB
- Exhibit 77 - B. Tannenbaum comment: 481 KB
- Exhibit 78 - Gottschalk and Greve comment: 1.89 MB
- Exhibit 79 - A. Menezes comment: 2.62 MB
- Exhibit 80 - G. Smith comment: 373 KB
- Exhibit 81 - L. Hedberg comment: 288 KB
- Exhibit 82 - A. Knopf comment: 245 KB
- Exhibit 83 - Romero for Baisch et al comment: 4.22 MB
- Exhibit 84 - E. Repperger comment: 539 KB
- Exhibit 85 - H. Thiede comment: 494 KB
- Exhibit 86 - B. McNeal comment: 303 KB
- Exhibit 87 - J. Kinsella comment: 189 KB
- Exhibit 88 - Kessden comment: 3 MB
- Exhibit 89 - S. Oien comment: 1.27 MB
- Exhibit 90 - Romero for Brown et al comment: 8.72 MB
- Exhibit 91 - T. Sanko comment: 353 KB
- Exhibit 92 - K. Monterey comment: 145 KB
- Exhibit 93 - S. Bowman comment: 897 KB
- Exhibit 94 - M. Cross comment: 2.12 MB
- Exhibit 95 - T. Davis comment: 2.89 MB
- Exhibit 96 - A. Peck comment: 12.98 MB
- Exhibit 97 - S. Brockway comment: 3.74 MB
- Exhibit 98 - T. Hornish comment: 2.24 MB
- Exhibit 99 - M. Wictor comment: 2.12 MB
- Exhibit 100 - C. Meyers comment: 14.57 MB
- Exhibit 101 - W. Way comment: 439 KB
- Exhibit 102 - W. Cormier comment: 491 KB
- Exhibit 103 - C. Elder comment: 2.79 MB
- Exhibit 104 - S. Abtahis comment: 1.25 MB
- Exhibit 105 - SHO comment: 744 KB
- Exhibit 106 - G. Morel comment: 6.52 MB
- Exhibit 107 - W. Schultheiss CV: 999 KB
- Exhibit 108 - AASHTO 2012 excerpts: 1.44 MB
- Exhibit 109 - Schultheiss Memo 11-3-17: 2.05 MB
- Exhibit 110 - City Staff PowerPoint Presentation: 3.86 MB
- Exhibit 111 - M. Young comment: 617 KB
- Exhibit 112 - M. Wictor comment: 19.49 MB
- Exhibit 112 - M. Wictor comment (with yellow highlighting): 19.79 MB
- Exhibit 113 - Memo form Bill Schultheiss 11-16-17: 994 KB
- Exhibit 114 - Charles D. Alexander CV: 126 KB
- Exhibit 115 - Alexander Presentation: 10.28 MB
- Exhibit 116 - PSRC - Population and Households: 1.22 MB
- Exhibit 117 - Direct Demand Models: 2.01 MB
- Exhibit 118 - Memo from Bill Schultheiss 06-20-17: 5.2 MB
- Exhibit 119 - A Policy on Geometric Design of Highways and Streets: 280 KB
- Exhibit 120 - AASHTO Bike Guite - Toole and Lagerwey: 1.18 MB
- Exhibit 121 - AASHTO BIke Guide - Design Imperative: 875 KB
- Exhibit 122 - WSDOT - Sect Exec Order No. E 1028.02: 836 KB
- Exhibit 123 - LOS for Shared-Use Paths: 3.46 MB
- Exhibit 124 - Charles Alexander Presentation Notes: 2.34 MB
- Exhibit 125 - Mark Cross Comments: 1.41 MB
- Exhibit 126 - Mr. Greve Comments: 6.93 MB
- Exhibit 127 - Charles Meyer Comments: 521 KB
- Exhibit 128 - Joanne Pietromonaco Comments: 486 KB
- Exhibit 129 - Ada McKee Comments: 399 KB
East Lake Sammamish Trail Segment 2B - Applicant Exhibits for Hearing Examiner
- Exhibit 70 - King County Part 1: 93.49 MB
- Exhibit 70 - King County Part 2: 55.41 MB
- Exhibit 70 - King County Part 3: 38.89 MB
East Lake Sammamish Trail Segment 2B - Additional City Exhibits for Hearing Examiner
- Exhibit 68: King County Public Comment Responses: 2.28 MB
- Exhibit 69: King County Subscription Service Email - Public Comment Responses: 108 KB
King County Response to Public Comments - From County Website as of October 16, 2017
- East Lake Sammamish Trail Segment 2B - King County Response to Public Comments: 1.75 MB
- East Lake Sammamish Trail Segment 2B - King County Response to Joint Public Comments: 170 KB
- King County Subscription Service Email re: Response to Public Comments: 106 KB
East Lake Sammamish Trail Segment 2B - Hearing Examiner Record as of October 4, 2017
- Exhibit 1: Staff Report: 4.65 MB
- Exhibit 2: Notice of Public Hearing and Staff Recommendation: 155 KB
- Exhibit 3: Land Use Application: 224 KB
- Exhibit 4: Shoreline Substantial Development Permit Application: 67 KB
- Exhibit 5: Affidavit of Applicant Status: 104 KB
- Exhibit 6: Project Narrative: 79 KB
- Exhibit 7: Exhibit 60% Revised Project Plan Set/Site Plan: 97.22 MB
- Exhibit 8: JARPA: 2.07 MB
- Exhibit 9: Record of Decision - FEIS: 791 KB
- Exhibit 10: SEPA Narrative: 303 KB
- Exhibit 11: Acceptance of Financial Responsibility: 128 KB
- Exhibit 12: Draft Technical Information Report: 56.5 MB
- Exhibit 13: Section 106 Programmatic Agreement: 347 KB
- Exhibit 14: Pre-Application notes (PRA2016-00334): 1 MB
- Exhibit 15: Critical Areas Affidavit: 226 KB
- Exhibit 16: Revised Critical Areas Study – July 2017: 47.25 MB
- Exhibit 17: Ordinance O2016-410: 1.4 MB
- Exhibit 18: Letter of Incomplete Application – November 15, 2016: 818 KB
- Exhibit 19: King County Response Letter to City Letter of Incomplete Application – November 30, 2016: 393 KB
- Exhibit 20: Title Reports submitted on October 19, 2016: 10.2 MB
- Exhibit 21: Ownership Binder submitted on November 30, 2016: 56.32 MB
- Exhibit 22: Letter of Complete Application – December 13, 2016: 926 KB
- Exhibit 23: Notice of Application – December 28, 2016: 574 KB
- Exhibit 24: Notice of Application – Affidavit of Mailing and Sign Posting: 32.86 MB
- Exhibit 25: Notice of Application – Affidavit of Seattle Times Publication: 585 KB
- Exhibit 26: Clarification to Letter of Complete Application – December 23, 2016: 1.72 MB
- Exhibit 27: March 1, 2017 process change letter: 1.17 MB
- Exhibit 28: Comment Matrix Log: 414 KB
- Exhibit 29: Public Comments – Part 1: 21.14 MB
- Exhibit 29: Public Comments – Part 2: 27.99 MB
- Exhibit 29: Public Comments – Part 3: 26.48 MB
- Exhibit 29: Public Comments – Part 4: 21.84 MB
- Exhibit 29: Public Comments – Part 5: 25.86 MB
- Exhibit 29: Public Comments – Part 6: 14.36 MB
- Exhibit 29: Public Comments – Part 7: 25.33 MB
- Exhibit 29: Public Comments – Part 8: 25.68 MB
- Exhibit 29: Public Comments – Part 9: 26.52 MB
- Exhibit 29: Public Comments – Part 10: 22.42 MB
- Exhibit 29: Public Comments – Part 11: 24.84 MB
- Exhibit 29: Public Comments – Part 12: 27.27 MB
- Exhibit 29: Public Comments – Part 13: 25.75 MB
- Exhibit 29: Public Comments – Part 14: 26.49 MB
- Exhibit 29: Public Comments – Part 15: 22.33 MB
- Exhibit 29: Public Comments – Part 16: 14.33 MB
- Exhibit 29: Public Comments – Part 17: 22.33 MB
- Exhibit 29: Public Comments – Part 18: 25.66 MB
- Exhibit 29: Public Comments – Part 19: 24.91 MB
- Exhibit 29: Public Comments – Part 20: 23.18 MB
- Exhibit 29: Public Comments – Part 21: 2.68 MB
- Exhibit 30: Notice of 120 Day Clock Exceedance – April 12, 2017: 165 KB
- Exhibit 31: Notice of 120 Day Clock Exceedance – Affidavit Email: 7.67 MB
- Exhibit 32: Notice of 120 Day Clock Exceedance – Affidavit of Mailing: 19.25 MB
- Exhibit 33: Notice of 120 Day Clock Exceedance – Affidavit of Sign Posting: 304 KB
- Exhibit 34: Notice of 120 Day Clock Exceedance – Affidavit of Seattle Times Publication: 757 KB
- Exhibit 35: Status of ELST Inglewood Hill Parking Lot SSDP Letter – April 12, 2017: 539 KB
- Exhibit 36: First Review and Request for Additional Information Letter – April 12, 2017: 3.41 MB
- Exhibit 37: Public Works Review Memorandum #1 – March 27, 2017: 250 KB
- Exhibit 38: Eastside Fire and Rescue Plan Review – March 30, 2017: 29 KB
- Exhibit 39: Sammamish Plateau Water Review – January 27, 2017: 352 KB
- Exhibit 40: Sammamish Plateau Water Plan Set Review – January 27, 2017: 45.27 MB
- Exhibit 41: Sammamish Plateau Water Notes – March 27, 2017: 70 KB
- Exhibit 42: The Watershed Company Memorandum – March 22, 2017: 598 KB
- Exhibit 43: Comment from Muckleshoot Indian Tribe – January 27, 2017: 63 KB
- Exhibit 44: Comment from Snoqualmie Indian Tribe – December 28, 2016: 29 KB
- Exhibit 45: Email correspondence from P. Reddy and Staff – March 22, 2017: 87 KB
- Exhibit 46: Email correspondence from S. Roberts, Staff and King County – May 22, 2017: 3.68 MB
- Exhibit 47: Email correspondence from M. Parrott and Staff – June 22, 2017: 2.79 MB
- Exhibit 48: Email correspondence from P. Harrell and Staff – July 24, 2017: 3.14 MB
- Exhibit 49: King County Response Cover Letter – July 11, 2017: 899 KB
- Exhibit 50: City Letter Comments Annotated and County Response Matrix – July 2017: 3.62 MB
- Exhibit 51: Public Works Comments Annotated and County Response Matrix – July 2017: 365 KB
- Exhibit 52: Sammamish Plateau Water Comments Annotated and County Response Matrix – July 2017: 2.36 MB
- Exhibit 53: Eastside Fire and Rescue Comments Annotated and County Response Matrix – July 2017: 101 KB
- Exhibit 54: Watershed Comments Annotated and County Responses including Response Matrix – July 2017: 960 KB
- Exhibit 55: Mitigation Sequencing Compliance Narrative – July 2017: 175 KB
- Exhibit 56: Shoreline No Net Loss Narrative: 106 KB
- Exhibit 57: Fish Passage Draft Technical Memorandum – February 26, 2015: 6 MB
- Exhibit 58: Fish Passage Final Technical Memorandum Supplemental – May 18, 2015: 606 KB
- Exhibit 59: Trail Demand Analysis Memorandum – June 20, 2017: 1.34 MB
- Exhibit 60: Trail Width Memorandum – June 20, 2017: 484 KB
- Exhibit 61: Updated Tree Inventory/Assessment Report – July 11, 2017: 790 KB
- Exhibit 62: Revised 60% Tree Preservation Plan: 8.9 MB
- Exhibit 63: Second Review Letter to County – August 23, 2017: 416 KB
- Exhibit 64: Public Works Review Memorandum #2 – August 22, 2017: 100 KB
- Exhibit 65: The Watershed Company Memorandum – September 25, 2017: 150 KB
- Exhibit 66: Fehr Peers Review letter – April 7, 2017 and Fehr Peers Review Letter – September 25, 2017: 298 KB
- Exhibit 67: Original and Updated Real Property Interests Memorandums from Kenyon Disend: 524 KB
East Lake Sammamish Trail Segment 2B - Applicant Response to City First Review
- County Response Cover Letter: 894 KB
- City Letter: 3.44 MB
- Response to City Letter: 162 KB
- The Watershed Company Comments: 778 KB
- Response Intro to The Watershed Company Comments: 49 KB
- Response to The Watershed Company Comments: 150 KB
- The Watershed Company Tables: 125 KB
- Revised Critical Areas Study - July 2017: 47.33 MB
- Public Works Comments: 218 KB
- Response to Public Works Comments: 137 KB
- Eastside Fire & Rescue Comments: 28 KB
- Response to Eastside Fire & Rescue Comments: 78 KB
- Sammamish Plateau Water District Comments: 346 KB
- Response to Sammamish Plateau Water District Comments: 2.01 MB
- Mitigation Sequencing Compliance Narrative: 171 KB
- Trail Demand Analysis: 1.31 MB
- Trail Width Analysis: 446 KB
- Shoreline No Net Loss Memo: 106 KB
- SEPA Narrative: 263 KB
- Arborist Report: 797 KB
- Revised Tree Preservation Plan Set: 9.24 MB
- Drainage Structures Technical Memo Draft - 2/26/15: 6.1 MB
- Drainage Structures Technical Memo Final - 5/18/15: 620 KB
- Revised 60% Plan Set: 106.55 MB
East Lake Sammamish Trail Segment 2B - City First Review
- SSDP2016-00415 ELST Segment 2B_Public_ltr_120 Day Clock Exceedance_signed: 538 KB
- SSDP2016-00415 ELST Segment 2B_Notice_of_120 Day Clock Exceedance: 167 KB
- SSDP2016-00415_ELST Segment 2B_First Review Letter_Final_4.12.17_signed: 3.41 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 1: 20.72 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 2: 28.08 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 3: 26.42 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 4: 21.61 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 5: 25.72 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 6: 14.2 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 7: 25.22 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 8: 24.71 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 9: 25.24 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 10: 22.08 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 11: 24.27 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 12: 27.02 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 13: 25.31 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 14: 26.67 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 15: 22.19 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 16: 14.3 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 17: 22.3 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 18: 25.51 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 19: 24.81 MB
- SSDP2016-00415 Segment 2B Public Comments combined_Vol 20: 23.02 MB
- SSDP2016-00415 Segment 2B & Inglewood Hill Joint Public Comments combined: 2.55 MB
- SSDP2016-00415_ELST Segment 2B Comment Matrix spreadsheet: 302 KB
- SSDP2016-00415_ELST Segment 2B & Inglewood Hill Joint Comment Matrix spreadsheet: 84 KB
- SSDP2016-00415 ELST Segment 2B_Muckleshoot Tribe email_1.27.17: 58 KB
- SSDP2016-00415 ELST Segment 2B_Snoqualmie Tribe email_12.28.16: 27 KB
- PW Review 1 Memo Segment 2B: 218 KB
- SSDP16-00415 ESFR Sam Trail 3-29-17: 28 KB
- SSDP2016-00415 ELST Segment 2B_Samm Plat comments_1.27.17: 346 KB
- SSDP2016-00415 ELST Segment 2B_Samm Pla comments_1.27.17_plan set notes: 45.24 MB
- SSDP2016-00415 ELST Segment 2B CAR peer review report - FINAL_3.22.17: 580 KB
East Lake Sammamish Trail Segment 2B - Applicant-Submitted Documents
- 0105010.PreliminaryDraftReport.10XX16: 11.46 MB
- ELST FEIS Vol I: 125.48 MB
- ELST FEIS Vol II: 29.64 MB
- ELST FEIS Vol III: 23.8 MB
- ELSTFEISNOA100520Final: 18 KB
- ELST-SSB2000buffmap: 2.24 MB
- ELST-SSB-AcceptFinancialResp: 126 KB
- ELST-SSBaddresses2000ftsept16: 1.41 MB
- ELST-SSB-AffidavitofAppStatus: 102 KB
- ELST-SSB-CAS2016-10-12: 32.78 MB
- ELST-SSB-CriticalAreaAffidavit: 248 KB
- ELST-SSB-HALF20161012: 93.02 MB
- ELST-SSB-JARPA: 2.03 MB
- ELST-SSB-LandUse: 219 KB
- ELST-SSBProject Narrative: 68 KB
- ELST-SSB-Sect106PrAg: 326 KB
- ELST-SSB-ShorelineSubDevForm: 66 KB
- ELST-SSB-TIRDraft: 56.8 MB
- ELST-SSB-Title Reports: 9.51 MB
- ELST-SSB-TreePresevation SHEETS20161012: 10.74 MB
- PRA2016-00334 clearing-grading clarification_final 10.18.16: 495 KB
- PRA2016-00334 ELST Phase 2B_pre-app notes: 1020 KB
- November 30 - East Lake Sammamish Trail: 379 KB
- OWNERSHIP BINDER ELST1: 29.86 MB
East Lake Sammamish Trail Segment 2B - City Documents
- Notice of Incomplete Application: 813 KB
- SSDP2016-00415 ELST Segment 2B_MEMO - Real Property Interest: 410 KB
- Letter of Complete Application: 921 KB
- Clarification to Complete Application Letter: 1.71 MB
- Notice of Application: 570 KB
- Letter Regarding Type 4 Processing: 1.16 MB
East Lake Sammamish Trail Segment 2B - Public Comments
- SSDP2016-00415 ELST Segment 2B comments rcvd 12.31.16: 146 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd. 1.2.17: 179 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.4.17: 149 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.5.17: 123 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.6.17: 405 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.9.17: 701 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.10.17: 3.87 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.11.17: 1.89 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.12.17: 4.95 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.13.17: 114 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.14.17: 213 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.15.17: 137 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.16.17: 9.98 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.17.17: 2.73 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.18.17: 1.43 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.19.17: 433 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.20.17: 103 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.21.17: 23.92 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.22.17: 20.34 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.23.17: 14.18 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.24.17: 28.11 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.25.17: 64.3 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.26.17: 25 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.27.17: 197 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.28.17: 9.11 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.29.17: 504 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.30.17: 120 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 1.31.17: 511 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.1.17: 100 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.2.17: 76 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.3.17: 325 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.4.17: 79 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.8.17: 173 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.10.17: 231 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.13.17: 15.1 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.16.17: 22.12 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.24.17: 62 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.26.17: 186 KB
- SSDP2016-00415 ELST Segment 2B comments rcvd 2.27.17: 14.41 MB
- SSDP2016-00415 ELST Segment 2B comments rcvd 3.6.17: 66 KB